Automating executive reporting on a giga-scale expansion program

Finding
Weekly and monthly executive reporting on the Makkah Holy Mosque Expansion ran on manually assembled feeds across progress, IPCs, bundles, quality tests, and manpower.
Evidence
End-to-end ETL pipelines in Power BI, Power Query, and Python replaced the manual steps on all five feeds; dashboards are delivered directly to the COO, the lead consultant, and the client PMO.
Standard
PMO reporting practice — single source of truth across project packages.
Consequence
Executives, the lead consultant, and the client PMO review the same current figures every reporting cycle.
Provenance
Role R-SBG — Saudi Binladin Group, April 2025 to present. Owner-verified account.

A governed project data hub on cloud infrastructure

Finding
Construction asset records and site visual-tracking streams needed one governed store with controlled access.
Evidence
An integrated data hub on Supabase and Cloudflare R2 serves the asset records and tracking streams under role-scoped access rules.
Standard
Data governance — row-level access control on a centralized store.
Consequence
Teams query the same governed dataset instead of exchanging files.
Provenance
Role R-SBG — Saudi Binladin Group, April 2025 to present. Owner-verified account.

Interval-versus-cumulative schedule performance intelligence

Finding
Executives needed schedule-variance visibility at two horizons — the reporting interval and the cumulative position.
Evidence
A VBA and Excel dynamic-arrays system produces both SPI perspectives and consolidates output to PDF without manual assembly.
Standard
Earned value trend analysis — SPI measured at interval and cumulative horizons.
Consequence
Schedule variance is read directly from consolidated packs each cycle.
Provenance
Role R-SBG — Saudi Binladin Group, April 2025 to present. Owner-verified account.

One data language for a corporate PMO

Finding
Corporate reporting fragmented across Planning, Cost Control, Procurement, Technical Office, and one further department; the same items carried different codes in different stores.
Evidence
A cross-functional audit diagnosed the fragmentation; a unified WBS/CBS/materials coding framework standardized the shared data language; automated ETL and multi-tiered dashboards consolidated the streams into one CEO-facing interface.
Standard
WBS/CBS standardization — one code system across departments.
Consequence
Reconciliation gaps between site procurement, warehouses, and engineering closed; routine data-preparation time fell by an estimated 40 percent.
Provenance
Role R-GMC — Green Modeling Contracting, September 2024 to March 2025. Owner-verified account.

A Python-to-Power BI pipeline for Primavera P6 XER analytics

Finding
Schedule-update analytics for consultancy deliverables ran on manual XER extraction.
Evidence
A custom Python pipeline parses and models XER datasets into Power BI, producing configurable reporting on execution progress, baseline variances, and critical-path tracking.
Standard
Primavera P6 XER data model — activity, relationship, and WBS fields.
Consequence
Executives and clients review current schedule analytics without manual re-extraction.
Provenance
Role R-RP — Rutherford + Partners LLC, April 2020 to April 2024. Owner-verified account.

Bidirectional Excel-to-P6 integration for forensic support

Finding
Schedule update cycles and forensic delay analyses across a multi-project consultancy portfolio carried heavy manual re-entry between Excel and P6.
Evidence
A bidirectional integration tool computes progress updates, remaining durations, and forecast dates; automated reconstruction models keep baseline-versus-actual variance tracking current.
Standard
Forensic schedule analysis support — extension-of-time substantiation inputs.
Consequence
Update cycles and forensic analyses complete faster with fewer transcription defects.
Provenance
Role R-RP — Rutherford + Partners LLC, April 2020 to April 2024. Owner-verified account.

Progress-monitoring systems across four mega-projects

Finding
Raw site production records had to become executive reporting — S-curves, labor histograms, lookahead schedules — on a fixed weekly and monthly cycle.
Evidence
Automated Excel and database systems converted site records into the required outputs for project directors and client PMOs; P6 schedule updates integrated WBS logic, resources, and CPM analysis to surface slippage trends and check baseline compliance.
Standard
Project controls reporting lifecycle — weekly and monthly cadence.
Consequence
Reporting cycles ran with reduced discrepancies between field execution, procurement, and commercial management.
Provenance
Role R-CCIC — CCIC Qatar, February 2007 to March 2020. Owner-verified account.